A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?

Respuesta :

Tundexi
Tundexi Tundexi
  • 17-12-2020

Answer:

1

Explanation:

The Formula for calculating Slack Time is as below:

Slack Time = Latest Completion Time - Earliest Completion time

When Latest Completion Time = 6 ; Earliest Completion time = 5

Slack Time = 6 - 5

Slack Time = 1

Thus,  the slack time for the activity is 1 . The essence of calculating this is to prevent delays in the project completion.

Answer Link

Otras preguntas

Which of the following choices is a fragment (an incomplete sentence)? Ever since my sister hacked my facebook account. I ve been very cautious. I never leave m
suggest three South African initiatives that adress:inequality in gender,rights of people living with HIV and violence against women and children
The graph below shows the total number of puzzle pieces packed in 3 jigsaw puzzle boxes of the same kind. COULD SOMEONE PLEASE HELP ME!!!!!!!
Factors that could hamper or block effective communication
4. For a drug addict, getting the drug becomes the single most powerful motivator in their life. A. True B. False
care sunt valorile lui a , b, si c daca a+2×b+3×c=19
Help with science do today
Which number is larger 0.775 or 0.95
The ban on liquor sales as outlined in the Eighteenth Amendment was called: New Deal Prohibition Progressivism
What was the policy called the Monroe Doctrine?