if 125 men can do a piece of work in 120days, how many men would be sufficient to do the same work in 100days?​

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 17-06-2021

Answer:

x =150 men

Step-by-step explanation:

Think of the total as workdays

125men* 120days = 15000 workdays

We still need 15000 workdays

100 days * x = 15000workdays

Divide by 100

x = 15000/ 100

x =150 men

Answer Link
akbusiness987
akbusiness987 akbusiness987
  • 17-06-2021

Answer:

150 men

Step-by-step explanation:

120 × 125 = 15000

15000 ÷ 100

150

Answer Link

Otras preguntas

Number of dinners = 125 Individual portion = 8 oz. Size of can = 32 oz.
algebra 2 unit 7 lesson 3
2s+(-4s) combine the like terms to make a simpler expression
Was the Roman legal system successful in uniting and stabilizing people
What is the answer for 2(-3+4 plz help me
American isolationism __________. a. ended with the onset of the great depression b. came to an end with the bombing of the u.s. naval base at pearl harbor c. e
2 ways which igneous rocks are used in everyday life?
When conducting an interview, use ________ questions to encourage the person you're interviewing to offer an opinion and not just a yes-or-no answer. select one
Why the jewish were thought to be spreading the black death?
Answer Please will rate and more!!!!!!!!!!!!!!!!!!!!!!!!!!