A construction company needs to remove 18 tons of dirt from a construction site. They can remove 2/3 tons of dirt each hour. How long will take to remove the dirt? Write your answer in simplest form

Respuesta :

wegnerkolmp2741o
wegnerkolmp2741o wegnerkolmp2741o
  • 21-07-2021

Answer:

27 hours

Step-by-step explanation:

Take the amount of dirt and divide by the amount per hour

18 tons ÷ 2/3 ton per hour

Copy dot flip

18 * 3/2

Rewriting

18/2 * 3/1

9*3 = 27

27 hours

Answer Link

Otras preguntas

How did the Aryans and Indians justify the use of the caste system?
How to get rid of roaches in an apartment permanently?.
Can anyone help please
Describe several ways of creating a good sleep environment.
a+ab when a =5 and b +2
What is the mass of 16. 6 x 10^23 molecules of barium nitrate.
A child with a weight of 430 N rides on a Ferris wheel, which has a radius of 17 m, and the linear velocity of the 3.5 m/s at any point on the circle. What is t
Brainliest if correct
brooooooooo help meeeeeeeeeeeee
1. The table shows the prices of 3 boxes of laundry detergent of different sizes. Which size box costs the least per ounce? Explain your answer. Size Price 150