A finishes a job in 10days,B finishes in 15days.if A and B work at it together, how many days will they take to complete the job​

Respuesta :

reinhard10158
reinhard10158 reinhard10158
  • 17-10-2021

Step-by-step explanation:

so, working together, in 1 day 1/10 + 1/15 of the work is done.

how many days (x) until we get 1/1 of the work done ?

x × (1/10 + 1/15) = 1

x × (3/30 + 2/30) = 1

x × 5/30 = 1

x×5 = 30

x = 30/5 = 6

so, together, they will finish the work in 6 days.

Answer Link

Otras preguntas

In what ways does the federal government step on the rights of the states? Why?
I need help to find the expanded form of 39,012
What is 14 divided by 1050?
Everett made three fifths of the baskets he shot. suppose he shot 60 baskets. how many did he make?
On a book shelf you choose the 11th book from the left and the 10th book from the right.  How many books are on the shelf?
Miss Bird can make 8 sculptures in 6 months.How many months will it take if she makes 12 sculptures?
What do we call elements that always travel in pairs?
Pencils are packed 10 to a box.  A classroom carton has 10 boxes.  Lee needs to buy 370 pencils.A.  How many boxes does lee need to purchase? Use place value to
I cant figure out what 14/15 - 7/12 is. I have tried for 30 minutes and I cant figure it out.
what is the hcf of 36 and 42