A team of 15 workers can do a job in 7 hours. How long would this work take if the team has 35 people?

Respuesta :

taskmasters
taskmasters taskmasters
  • 28-04-2017
We would expect that the answer is a small value since there will be a total of 35 people who will work.
7 hours/15=x/35 workers
(7*15)/35=x hours
3hours=x


Therefore, the 35 people will work only for 3 hours. 
Answer Link

Otras preguntas

Solve the volume formula V= lwh for l. a. l=Vwh b. l=V/wh c. l=V/h+w d. l=wh/V
Which of the following statements is false? a. The product of two rational numbers is always irrational. b. The sum of a rational number and an irrational numbe
We need to urge our city planners to say goodbye to the urban sprawl that has engulfed our nation like a tidal wave in the last few decades, and instead build
How can creation myths influence how the history of the world or a society is viewed?
how many numbers are equal to the sum of two odd, one digit numbers
Using the quadratic formula to solve 7x2 – x = 7, what are the values of x?
Categorize the following analogy: Hump is to camel as shell is to snail. a. object and location b. part to whole c. performer and action d. object and funct
What is 21/8 as a mixed number? Please Help Quickly!!!!!!
In order for work to take place the energy present must be related to the movement of the object. a. the force applied must be a balanced force resulting in mo
How would i solve for force when there are multiple accelerations?