A network diagramming technique in which boxes represent activities is known as a(n) _____.

a. pdm

b. cpm

c. adm

d. pert

Respuesta :

StrongBad
StrongBad StrongBad
  • 16-11-2017
PERT is a review technique/tool, so that can't be it. CPM is Critical Path Method, and you can use a PDM or an ADM to chart it. 

The easy way to remember this answer, is that you write on the arrow when using the "arrow diagram method."  

So the answer is "a. pdm" (precedence diagram method).
Answer Link

Otras preguntas

answer this question as soon as possible.
Find the nth derivative for y = e^(2x)sin (5x)​
How many 1 1/2-liter bottles of water does it take to fill a 16-liter jug?
ARITHMETIC MEANS - If a;b;c form an arithmetic sequence then: 1. Find the arithmetic mean between 8 and 20. 2. Calculate four arithmetic means between 2 and 3
After my work in this chapter, I am able to communicate about leisure activities, and I am able to indicate plans and intentions. Match each verb with an approp
At the grand opening of an amusement park every three out of 20 visitors receive a free ride ticket how many people can expect a free ticket out of 100 visitors
kesler science plate boundaries assess it part 2
did a reaction happen? if one did, what is the complete ionic and net ionic equation
What are 5 animals that are in the tree huger article
how do i find the value of x on this?? please and thank you i dont know what this is called so i dont know how to do the equations and whatnot..